丽江华坪硅片加工和组件制造生产线项目 Silicon Processing and Module Manufacturing Production Line Project in Huaping County, Lijiang

发布时间:2021-12-31 15:17
来源:本站
作者:
点击:2622次

Project Overview

1. Project Name

丽江华坪硅片加工和组件制造生产线项目

Silicon Processing and Module Manufacturing Production Line Project in Huaping County, Lijiang

2. Project Industry

New Material Industry

3. Project Site

Shilongba Clean Energy Carrying Industrial Park, Huaping Industrial Park, Huaping County

4. Project Overview

Silicon Processing and Module Manufacturing Production Line Project in Huaping County, Lijiang, is located in Shilongba Clean Energy Carrying Industrial Park, Huaping Industrial Park, Huaping County, with a total investment of RMB 5 billion and a land area of 200 mu. The project mainly constructs zones such as production, supporting facilities, logistics and warehousing, and comprehensive service, including production line of diamond wire slicing, highly-automated assembly production line, power supply and distribution system, cooling water system, inert gas supply system, vacuum system and A/C air filtration system required for the production environment, raw materials warehouse, chemicals warehouse, office building and R&D center. After completion, the project will turn Huaping into a stronger PV electronic industry cluster, thus driving the local economic development, even the development of the opto-electronics industry in China and Southeast Asia.

Project Implementation Background

1. Industrial Policies

10 Measures of Lijiang to Support High-quality Development of Private Economy

Lijiang Talent Program

Implementation Plan for "Eight Hundred" Talent Program in Lijiang

Implementation Opinions of People's Government of Yunnan Province on Promoting the Development of Integrated Hydropower Silicon Material Processing and Manufacturing Industry

Implementation Opinions of People's Government of Lijiang City on Accelerating the Development of Clean Energy Industry

2. Upper-Level Plan

Industrial and Informatization Development Planning of Huaping County during the 14th Five-Year Plan

Project Construction Plan

1. Project Site Overview

1. Project Site: Shilongba Clean Energy Carrying Industrial Park is located in Shilongba Town, Huaping County, adjacent to Panzhihua, Sichuan, between Huaping-Panzhihua Expressway and Huaping-Panzhihua Second-class Highway. It is away from Shilongba Toll with a straight-line distance of less than 1 km and only 3.6 km away from Guanyinyan Hydropower Station, with distinctive advantages on location, transportation and power.

2. Shilongba Clean Energy Carrying Industrial Park is bordered by Huaping Overlimit Transportation Management and Unloading Monitoring Point to the north, Xinwang River to the south, Shilongba Police Station to the west and Futian Central School to the east.

3. Land purchasing and reserve have been done without involving "three red lines".

2. Construction Duration

4 years

3. Investment Estimate

1. Investment Estimate: RMB 5 billion

2. Fund Raising: Self-raised by enterprises or loans

4. Project Content

1. Project Positioning:

With Huaping Industrial Park as the carrier, the project relies on monocrystalline silicon production of LONGi to form a PV electronic industry cluster, build a Silicon Industry Demonstration Base of "silicon rod - wafer - cell - processing components" in northwest Yunnan, extend the industrial chain, increase added value and reduce logistics costs, so as to drive local economic development, even the development of the opto-electronics industry in China and Southeast Asia once being completed.

2. Functional Zoning:

Production zone, supporting facilities zone, logistics and warehousing zone and comprehensive service zone.

3. Project Content:

Production line of diamond wire slicing: The cutting device of the diamond wire monocrystalline silicon rods comprises the large bottom frame, portal frames, wire arranging and mounting frames, tension motor mounting frames, tension motors, tension arms, worktable head base, worktable tail base, wire arranging part, wire winding and unwinding part, wire deviation detecting part, cutter feeding units, transition guide wheels and tension guide wheels, wherein crystal rods are clamped by the worktable head base and the workbench tail base; and the crystal rods are controlled to rotate around axes of the worktable head base and the worktable tail base.

Highly-automated assembly production line: Utility model for the solar energy industry, especially for the automated production line of monocrystalline silicon.

Supporting facilities zone: Power supply and distribution system, cooling water system, inert gas supply system, vacuum system and A/C air filtration system required for the production environment.

Logistics and warehousing zone: Raw materials warehouse and chemicals warehouse.

Comprehensive service zone: Office building and R&D center.

Project Advantages

1. Industrial Basis

At present, Xi'an LONGi, the world-leading monocrystalline silicon rod enterprise, has in-parked in Huaping Industrial Park. The Phase I and II projects of Lijiang LONGi (Huaping LONGi) have achieved an output of RMB 5.6 billion, with the 46,000 t of monocrystalline silicon rods in 2020; and the commencement ceremony of the Phase III project was held on 30 March, 2021, and is under site levelling construction. It is planned to be completed and put into operation by the end of December, which can provide materials for the project.

2. Resource Advantages

Mineral Resources: Huaping is rich in mineral resources with mining value, including coal, limestone, bauxite, graphite ore, dolomite, granite, etc. Huaping is one of the 200 major coal-producing counties in China.

Power Resources: Six large hydropower stations, namely Liyuan, A'hai, Jinanqiao, Longkaikou, Ludila and Guanyinyan on the mainstream of Jinsha River in Lijiang have been completed and put into operation, with a total installed capacity of 13.76 million kW, a theoretical annual power generation of 65 billion kWh, and an average annual power generation of 58.5 billion kWh.

Among which, Guanyinyan Hydropower Station is located in Huaping County, with an installed capacity of 3 million kW and an annual power generation of 12 billion kWh.

Water Resources: Huaping County belongs to Jinsha River system and has two rivers, Xinzhuang River and Wumu River. It has one medium-sized reservoir and 33 small reservoirs Type I and II.

Land Resources: The layout of Huaping Industrial Park complies with "one zone, three parks", with a total planned area of 32.13 km2, among which, Shilongba Clean Energy Carrying Industrial Park has a planned area of 18 km2 and is of sufficient land capacity.

3. Supporting Conditions

At present, Shilongba Clean Energy Industrial Park of Huaping has reserved 30 GW wafer project land in the lot adjacent to the crystal pulling workshop, and the upstream rod pulling project can directly provide the raw materials required for cell project. The main road that connected to Lijiang-Panzhihua Expressway in and out of the Park has been completed and water supply and power supply systems have been constructed in the Park. Site leveling is finished and roads, sewage treatment plant and living supporting facilities are complete, so the construction can be started quickly.

Power Supply: There is one 220 kV substation and two 110 kV substations in the Industrial Park, and one new 220 kV substation and four 110 kV substations are being built for the Park's incremental distribution network project. At the same time, one 500 kV substation will be planned and constructed.

Water Supply: The Industrial Park is equipped with a water supply plant with a daily water supply of 19,000 m3.

Sewage Treatment: The Industrial Park is equipped with a sewage treatment plant with a daily treatment of 20,000 m3.

The supporting quartz crucible Phase I has produced 30,177 quartz crucibles in 2020, reaching an output value of RMB 82.02 million.

4. Location and Transportation

Road: National Highway G353 and Provincial Highway S217 in Huaping County run across the province.

Lijiang-Panzhihua Expressway and Huaping-Panzhihua Second-class Highway in the Industrial Park run across the territory.

Aviation: Huaping County enjoys a well-developed airline network and obvious aviation advantages, with 80 km from Panzhihua Baoanying Airport, 250 km from Lijiang Sanyi International Airport, and 360 km from Kunming Changshui International Airport.

Railway: Panzhihua-Dali (Lijiang) Railway, which has been included in the national railway network plan, runs through Huaping Industrial Park. The planned freight station is 2 km away from the project site. Huaping County Clean Energy Industrial Park is only 20 km away from Panzhihua Geliping Railway Station of Chengdu-Kunming Railway, which can access the national railway network through Panzhihua Geliping Railway Station.

5. Development Opportunities

With Huaping Industrial Park as the carrier, the project relies on monocrystalline silicon production of LONGi to form a PV electronic industry cluster, build a Silicon Industry Demonstration Base of "silicon rod - wafer - cell - processing components" in northwest Yunnan, extend the industrial chain, increase added value and reduce logistics costs, so as to drive local economic development, even the development of the opto-electronics industry in China and Southeast Asia once being completed.

Factors Guarantee

1. Production Operation Cost

Electricity Price: The green hydropower with a Total installed capacity of 13.76 million kW in Lijiang, has provided sufficient and stable energy guarantee for the integrated development of hydropower silicon materials. The annual average electricity price for Huaping Industrial Park Clean Energy Industry Project is lower than the current electricity price in other regions. The electricity price is around RMB 0.35/kWh;

Water Price: Industrial water price is RMB 3.8/m3.

Labor Resources: Labor costs are low in Huaping County, with the average wage of on-the-job employees in non-private units in 2020 at RMB 4,215/month and the minimum wage in Huaping County at RMB 1,350/month.

Project Policy Support

1. Business Environment Improvement

The project has a superior marketing environment and a high degree of maturity, with the support of government policies.

2. Fiscal and tax preferential policies at all levels available to enterprises such as provincial/municipal/district/county/park investments

1. The average cost of industrial land in Shilongba Clean Energy Carrying Industrial Park (land acquisition compensation and approval fee) is RMB 164,000 per mu. If ownership is obtained through enterprise transfer, the government will give the transfer land price the maximum preference. At the same time, a flexible transfer mechanism of industrial land can be adopted to minimize the cost of land for enterprises by renting before transferring.

2. Rent-free Settlement: For enterprises attracted from investment promotion to lease standard workshops in Industrial Park, all leasing fees are waived for the first three years according to the scale of the enterprise, and the leasing fees are reduced by half for the next three years.

3. Tax Preference: Tax preferential policies will be implemented faithfully, and appropriate awards will be given depending on the tax contribution of enterprises.

4. One-stop Service: Full agent services for park settlement is implemented to create good conditions for project construction.

5. Talent Support: High-level management talents of enterprises attracted from investment promotion are provided with supporting services such as household registration, offspring schooling, spouse relocation, tourism reception, social insurance and housing in accordance with the Green Channel Services for the Introduction of High-Level Talents in Lijiang City.

6. Multiple Policies Support: The enterprises attracted from investment promotion can enjoy a series of preferential measures such as 10 Measures of Lijiang to Support High-quality Development of Private Economy, Lijiang Talent Program and Implementation Plan for "Eight Hundred" Talent Program in Lijiang issued by Lijiang City.

7. Industrial Policies: Policies related to Implementation Opinions of People's Government of Yunnan Province on Promoting the Development of Integrated Hydropower Silicon Material Processing and Manufacturing Industry and Implementation Opinions of People's Government of Lijiang City on Accelerating the Development of Clean Energy Industry are available.

Benefit Analysis

1. Operation Mode: Self-operated

2. Profit Model:

The project is made profits from selling monocrystalline silicon wafers, solar cell modules, secondary conduits, electronic copper foil, electronic soldering, optical fiber materials, flat panel display materials, electronic memory and other products.

3. Economic Benefits:

The project investment is estimated to RMB 5 billion, covering an area of 200 mu, with a construction period of 4 years. It is estimated that the annual operating revenue is RMB 4.565 billion, the annual profit and tax is RMB 1 billion, and 2,000 employees are employed.

Investment Promotion Direction

Beijing, Hangzhou, Ningbo, Tianjin and Luoyang

Cooperation Pattern

Cooperation, joint venture, and sole proprietorship

Contact Information

Contact Authority: Investment Promotion Bureau of Huaping County

Contact Person: Du Qinghong

Tel.: 0888—6126767

E-mail: 316381710@qq.com

本站点由云南省投资促进局主办
版权所有 © 云南省投资促进局 未经同意不得转载

滇公网安备 53011102001196号

联系方式
0871-67195654
ynstzcjj@yn.gov.cn

云南招商官方微信

法治在线官方微信

国务院“互联网+督查”

营商环境投诉举报

营商环境问卷调查

管理员登录
平台入口